Web Server Installation Guide Page 22
CDU-AC5
In addition, the user may step backwards or forwards through the schematics they have
previously viewed by clicking the buttons shown below,
6.3 CDU Schematics
6.3.1 Overview
The overview schematic provides an at-a-glance status of the CDU. It is presented as a piping
backdrop onto which are positioned a number real-time data points. These data points are
either numerical values or state bitmaps.
For the secondary pumps and fill pump, the following bitmaps are used to indicate their state,
For the heat exchanger valves the following bitmaps are used to indicate their state,
Pump OFF
Pump ON
Valve Closed
Valve Open